Cash Flow Risk Factors in Construction Projects That Can Be Minimized with Technology | Part 2
In the previous blog post in this series, we talked about how the risk of delayed conditional payments can be minimized with better documentation management.
Here we will focus on how an early-warning system can help manage the risk of delayed project overheads and prelims.
First let’s break down the jargon.
In the Indian context of a typical construction project, ‘overhead’ refers to the costs associated with running the project’s head office administration (as per the terms in the contract), plus the interest incurred on the project’s working capital. This can include the cost of running the estimation department, the costs associated with the finance department at the head office who are processing the invoices with vendors, the payment certificates from the client, etc. In some countries, it includes property costs, finance charges on loans, insurances, staff, taxes, external advisors, and marketing and tendering activities. Sometimes, the contracting organizations calculate a percentage against project costs to be set against each project, typically somewhere between 2.5% and 10% to cover head office services.
Project Preliminary costs or Prelims are site-specific costs. They are the costs directly related to the running of the project, but not accounted under the package of works required by the contract. It includes site management, site staff, site operating expenses, temporary services involving site maintenance like security and environmental protection control etc. So ‘prelims’ and ‘work sections’ together lay out everything required to complete the works specified in the contract. For that reason, ‘costs attached to preliminaries’ are referred to as just ‘preliminaries‘ or ‘prelims‘, or as ‘site overheads‘, or general cost items or expenses. The preliminaries may also list items the main contractor is to provide on behalf of the Employer such as client’s offices, site vehicles, PPE etc.
Simply put, prelims are costs specific to a particular project whereas overheads are head office costs associated with transactions conducted for that project. Obviously, delaying either would be detrimental to not only the project’s progress but to the relationships between project parties.
How SmartProject can streamline the management of overhead and prelims costs.
Overhead and prelim costs are borne on a monthly basis and typically paid during the duration of the contract. So if cash flows tighten up, managing these monthly costs can become very challenging. This is where an integrated system like SmartProject comes in handy. It keeps meticulous track of work progress and makes sure that managers never get caught by surprise.
In SmartProject, managers can monitor the project’s progress in real time so effectively that if it seems unlikely that the contract will get completed on schedule, as often happens, they have an early heads-up and can take action pre-emptively rather than fire-fighting or damage control later.
For example, if you know ahead of time that early progress towards the scheduled milestone is slow, instead of waiting until the milestone is actually missed, you can act preemptively. You could negotiate proactively with the client instead of waiting for the last minute; you could call him early on and discuss the possibility of extending the prelims payment period. If the client refuses, you could make a provision from your contingency budget, so you have the money required to pay for the prelims. And so on.
Moreover, SmartProject also has the provision to forecast completion periods of delayed tasks and provides expected cash flows. This will greatly aid top management to take necessary pre-emptive control measures as necessary to reduce the financial burden on the project and company’s bottom line.
Projects are a constant juggling act with very little margin for error, and that is unlikely to change, but having an integrated information management system could give managers a bit more control when it comes to managing tight cashflow situations. That little bit of control could make all the difference, and keep work going even in unfavorable circumstances.
Expert in agile, predictive and hybrid project management. Researches on the application of Artificial Intelligence for better project outcomes. Works as a domain expert at Wrench Academy, the knowledge management division of Wrench Solutions, the makers of Smart Project Digital PMO.
Related Posts
Upcoming Trends in Enterprise Project Controls and Performance with PMIS
There’s increasing awareness about digital technology in project management, about how the features of a project management information system impact project controls and performance and how a digital project management system can enhance EPC project…
- 11 Sep 2024
What is an Effective EPCM Management System?
EPC and EPCM systems are becoming so widespread these days that its hard to imagine a successful project being completed without one. But what would be the right kind of system to invest in? Today…
- 04 Sep 2024
Archives
- September 2024
- August 2024
- July 2024
- June 2024
- May 2024
- April 2024
- March 2024
- January 2024
- December 2023
- November 2023
- September 2023
- August 2023
- July 2023
- June 2023
- May 2023
- April 2023
- March 2023
- February 2023
- January 2023
- December 2022
- November 2022
- September 2022
- June 2022
- May 2022
- April 2022
- March 2022
- January 2022
- November 2021
- October 2021
- July 2021
- June 2021
- May 2021
- March 2021
- February 2021
- January 2021
- December 2020
- November 2020
- September 2020
- August 2020
- June 2020
- April 2020
- March 2020
- February 2020
- January 2020
- November 2019
- October 2019
- September 2019
- August 2019
- April 2019
- March 2019
- December 2018
- October 2018
- September 2018
- August 2018
- July 2018
- June 2018
- May 2018
- April 2018
- January 2018
- November 2017
- October 2017
- September 2017
- May 2017
- April 2017
- March 2017
- February 2017
- January 2017