Wrench Solutions - Project Management Information System
MENUMENU
  • Products
        • SmartProject Suite
          • SmartProject DMS
          • SmartProject EDMS
          • SmartProject EPC MS
          • SmartProject PMIS
          • SmartProject Digital PMO
        • SmartProject Features
          • BIM Management
          • Schedule & Progress Management
          • Procurement Management
          • Construction Management
          • Cost & Cashflow Management
          • Contract Management
          • Resource Management
          • Project Quality Management
          • Safety Management
          • Risk Management
          • Snagging & Close Out
        • By Type of Companies
          • Owner
          • PMC
          • Engineering Consultant\Architect
          • EPC Contractor
          • General Contractor
          • Equipment Suppliers
        • By Industries
          • Chemicals & Process
          • Infrastructure & Construction
          • Oil &Gas
          • Railways
          • Renewable Energy
  • Customers
    • Customers List
    • Projects
    • Customer Journey
    • Testimonials
    • Case Studies
  • Resources
    • Resource Centre
    • Blog
    • Knowledge Hub
    • Podcasts
    • Support
    • Whitepaper
    • Product Related
      • Technology
      • FAQ
    • Certifications
    • Webinar
    • Integrations
  • Company
    • About Us
    • Wrench Academy
    • Partners
    • Careers
    • News & Events
    • Contact Us
  • Request Demo
CONTACT USREQUEST DEMO

Schedule Development & Baselining

Home Schedule Development & Baselining

Schedule Development & Baselining

Learning Objective 

Upon successful completion of this module, you will ;

  • Master the steps involved in scheduling 
  • Understand the significance of critical path 
  • You will also learn about float, buffer, lag, lead, fast tracking, crashing and their impact on project duration 
Effort required – 30 minutes

 Lesson Introduction 

Upon successful completion of this module, participants will gain good understanding of the steps involved in developing and optimizing project schedules.  

Level : Basic  

Diagram#1 Develop schedule mind map  

  1. Inputs 
  • Work breakdown structure (WBS)  
  • Work packages  
  • WBS dictionaries  
  • Scope document  
  1. Steps performed 
  • Decompose the work packages into activities  
  • Estimate activity resources and durations  
  • Sequence activities based on their dependencies  
  • Arrive at the critical path  
  • Optimize the schedule by adjusting leads, lags, crashing, fast tracking, resource leveling etc  
  • Baseline the schedule  
  1. Decompose the work packages into activities  

Diagram#2 Scope to Activity decomposition sequence  

Every project starts with the high level scope, which gets elaborated into detailed scope. The detailed scope is decomposed into work breakdown structure (WBS). At the lowest level of the WBS are the work packages. The work packages are decomposed further into activities.  

  1. Estimate activity resources and durations 
  • Analogous estimation – Arriving at the estimate by comparing with a past similar activity  
  • Parametric estimation – Based on indexes (cost per square feet, time per square feet)  
  1. Sequence activities based on their dependencies 

Diagram#3 FS, FF, SS, SF – The four types of activity dependencies  

  1. Arrive at the critical path

Diagram#4 Activity on arrow diagram  

The longest path in the network is the critical path. In the diagram above, the duration of the path A,B,D is 25, and the duration of the path A,C,D is 30, hence A,C,D is the critical path. The activities on the critical path should not slip. If they slip, the project will slip. If any of the activities on the path A,C,D slips by 1 day, the project duration will become 31. Even if there is a delay of 5 days on path A,B,D , the project will not slip.  

  1. Optimize the schedule by adjusting the leads and lags, buffer, float, fast tracking, crashing,resourceleveling 

Lag – waiting time between two tasks 

Diagram#5 Lag  

Lead – Parallelism between two tasks  

Diagram#6 Lead  

Buffer – In projects, one encounter unforeseen contingencies, and we create buffers to deal with them. For example, in the diagram below, if everything goes as per plan, construction can be completed in 3 days time. For dealing with contingencies a buffer of 2 days is added, and the total duration of the task becomes 5.  

Diagram#7 Buffer 

Float – The amount of time an activity can be delayed without affecting the early start date of the subsequent activity. Activities on the critical path will have zero float. An understanding of the amount of float available helps the planner to optimize resource deployment. For example, if a task with very low float is slipping, one can always release resources from a task with lot of float and deploy them in the slipping task. 

Diagram#8 Float  

Resource leveling – When we start allocating resources to tasks, some of the resources can be over loaded, where as some under loaded. The process of optimizing the resource loading against tasks by ensuring that all resources are almost equally loaded is known as resource leveling.  

Fast tracking – Trying to do things in parallel, which were originally scheduled sequentially  

Crashing – Trying to reduce the duration of a task, by deploying more resources into it.  

After the creation of the schedule, we apply all the above mentioned concepts to fit the schedule within the acceptable duration and cost. Once the schedule optimization is completed, the schedule is approved and baselined.  

  1. Baseline the schedule– Version control of the schedule 

Outputs  

  1. Schedule baseline  

Summary

 
The longest path in the project network is the critical path. In other words, it is the shortest possible time in which a project can be completed. Activities on the critical path have zero float. Sometimes, projects may have multiple critical paths. In that case, project management becomes complex. Effective project managers not only track the critical paths, but also will track paths with minimal floats to prevent project slippage. To recover from slippages or to speed up project execution, one may fast track or/and crash activities on the critical path. 
 

Exercise

 
Take a work package from any of your projects. Decompose it into activities. Estimate the activity durations. Using either the Activity on Node (AON) or Activity on Arrow (AOA), arrive at the critical path. 
 

Request a Training Course Today!

GET TRAINED

Company

  • About us
  • News
  • Contact us
  • Careers

Products

  • EDMS/CDE
  • Bim Management
  • Schedule & Progress Management
  • Cost Management
  • Procurement Management
  • Construction Management
  • Resource Management
  • Quality Management
  • Safety Management
  • Risk Management
  • Snagging and Project Closure
  • Integrations
  • Construction Monitoring & Control
  • Contract Management
  • Project Portfolio Monitoring

By Companies

  • Owner
  • PMC
  • Consultant
  • EPC Contractor
  • General Contractor
  • Equipment Suppliers
Construction Management Leader
G2 high performer
Acceptable Use Policy | Privacy Policy

© 2025 Wrench Solutions. All rights reserved.

loading

Please wait while you are redirected to the right page...

By using our site you agree to our use of cookies to deliver a better site experience. To find out more about cookies, what they are and how we use them, please see our privacy policy.OkDeclinePrivacy policy