Wrench Solutions - Project Management Information System
  • Solutions
        • Type of Companies
          • Owners / Developers
          • Engineering Consultants
          • EPC Contractors
          • Equipment Manufacturers
          • General Contractors
          • PMC
          • Capital Project Investors
        • Industries
          • Oil &Gas
          • Transportation
          • Infrastructure & Construction
          • Chemical & Process
          • Renewable Energy
          • Water & Wastewater
          • Metals & Mining
          • Datacenter & Fitouts
          • AEC
          • Power Generation & Transmission
          • Marine
        • Roles
          • Project Directors
          • Project Managers
          • Planning Engineers
          • Engineering Managers
          • Document Controllers
          • Checkers and Reviewers
          • Client Project Manager
          • Designers & Draftsmen
          • Vendors
  • Products
        • SmartProject Suite
          • SmartProject DMS
          • SmartProject EDMS
          • SmartProject EPC MS
          • SmartProject PMIS
          • SmartProject Digital PMO
        • AI Agents
          • AI Control Tower
          • Contracts AI Agent
          • Bid Review AI Agent
          • Engineering Reviewer AI
          • Asset Intelligence AI
          • AI Analyser
        • SmartProject Features
          • Planning & Project Controls (5)
          • Engineering & Design Management (15)
          • Procurement & Contract Management (9)
          • Construction & Execution (8)
          • Monitoring, Control & Collaboration (3)
          • Commercial & Measurement (2)
          • Commissioning, Handover & Closure (4)
          • Integrations & Ecosystem (4)
          • Mobility & Field Enablement (1)
          • All Features (51)
  • Why Wrench
        • Why Wrench
          • SmartProject EDMS vs other EDMS
          • SmartProject EDMS vs Email + Excel
          • SmartProject EDMS vs ERP + DMS
          • SmartProject PMIS vs Traditional PM tools
          • SmartProject PMIS+ ACC
          • SmartProject PMIS+ Primavera
          • SmartProject Compliance to ISO 19650
          • SmartProject Compliance to ISO 21500
          • SmartProject Compliance to PMI
        • Customers
          • Customers List
          • Projects
          • Testimonials
          • Case Studies
  • Resources
        • Resource Centre
        • Blog
        • Podcasts
        • Wrench Talk
        • Webinar
        • White Paper
        • Product Related
          • Technology
          • FAQ
  • Company
        • About Us
        • Wrench Academy
        • Partners
        • Careers
        • News & Events
        • Wrench Foundation
        • Contact Us
        • Certifications
  • Book a Demo
SupportBook a Demo

Earned Schedule Management (ESM)

Home Earned Schedule Management (ESM)

Earned Schedule Management (ESM)

Lesson Objective

Introduce the participant to Earned Schedule Management

Effort required – 30 minutes 
 

Lesson Introduction

For projects which has to focus primarily on the schedule only, Earned Value Management becomes an over kill. More than that, at the completion of the project, schedule variance will be shown as zero even for a late project because towards the end of the project both planned value (PV) and earned value (EV) will be same for a completed project.

Earned Schedule (ES) is a breakthrough analytical technique that resolves the EVM dilemma.  It is derived from and is an extension to EVM.  No additional data is needed for acquiring the ES measures; only the data from EVM is needed.  In contrast to the cost-based indicators from EVM, the ES schedule performance indicators are time-based, making them easier to comprehend.  The ES indicators provide a status and predictive ability for schedule, analogous to the facility for cost using EVM.

Formulas of Earned Schedule Management

Earned Schedule (ES) – The time point at which the project’s earned value was supposed to be the planned value.

Actual Time (AT) – Time units till the review date

SV (t) = Schedule Variance = Earned Schedule – Actual time

Schedule Performance Index SPI (t) = ES / AT (time units)

Estimated Duration (ED) = Planned Duration (PD) / SPI(t)

Estimated Completion Date (ECD) = Start_date + ED

Example

Consider a project whose duration from the start date till the end date is 200 days.

Let us assume that we are doing the review of the project on the 100th day.

As per the assumption during planning, the team is supposed to complete 2 units per day. So, at the end of 100 days, the team is supposed to complete 100×2 = 200 units

Planned Value = (PV) = 200

Actually, the team completed only 180 units

Earned Value = (EV) = 180

If things have gone as planned ( at the rate of 2 units per day), the team would have accomplished 180 units in 90 days’ time.

Earned Schedule (ES) = 90

Actual time units till review date (AT) = 100

Schedule Variance (t) = SV(t) = 90-100 = -10

Schedule Performance Index (t) = SPI(t) = ES/AT = 90/100 = 0.9

Estimated duration of the project (ED) = Planned Duration (PD) / SPI(t) = 200 / 0.9 = 222 days

Estimated Completion Date of the project = Start Date + ED = Start date + 222 days

Conclusion

For projects for which monitoring cost is not as important when compared to monitoring and forecasting schedule, Earned Schedule Management (ESM) is the most appropriate method and it does not ask for any additional data apart from Planned Value and Earned Value. 

Exercise 

For the following case, work out the schedule forecast. 

Request a Training Course Today!

GET TRAINED

Company

  • About us
  • News
  • Contact us
  • Careers

Products

  • EDMS/CDE
  • Bim Management
  • Schedule & Progress Management
  • Cost Management
  • Procurement Management
  • Construction Management
  • Resource Management
  • Quality Management
  • Safety Management
  • Risk Management
  • Snagging and Project Closure
  • Integrations
  • Construction Monitoring & Control
  • Contract Management
  • Project Portfolio Monitoring

By Companies

  • Owner
  • PMC
  • Consultant
  • EPC Contractor
  • General Contractor
  • Equipment Suppliers

Resources

  • Resource Centre
  • Blog
  • Case Studies
  • Projects

Downloads

Acceptable Use Policy | Privacy Policy

© 2026 Wrench Solutions. All rights reserved.